Designing a multi-site data-center platform for continuous PUE optimization

A 2017 IPOS proposal connects metering, common KPI definitions, equipment diagnosis and measurement and verification. Its numerical targets remain proposal-stage expectations.

01 · CASE ANALYSIS

Move from one diagnosis to ongoing management

The proposed platform combines total electricity, IT electricity, cooling electricity and cooling-unit, chiller and tower data across multiple data centers.

Changing IT loads, weather and equipment states mean that a previously identified operating point cannot be assumed to remain optimal.

02 · CASE ANALYSIS

Keep targets separate from results

The first 24-month target was PUE 1.77 → 1.70, with expected annual electricity savings of 6.5 GWh and expected cost savings of approximately KRW 753 million.

These were pre-implementation project targets. The source does not confirm achievement of those quantities.

Proposal targets — not achieved savings
ItemSource value
First-stage period24 months
PUE target1.77 → 1.70
Expected electricity saving6.5 GWh/year
Expected cost savingApproximately KRW 753 million/year

03 · CASE ANALYSIS

Define the platform layers

Use metering/BMS acquisition, common data definitions and quality checks, KPI/benchmarking, diagnosis/modeling, and optimization/M&V as separately testable layers.

Compare peers with consistent meter boundaries and aggregation periods. Normalize for IT load, weather, cooling architecture and redundancy before ranking sites.

04 · CASE ANALYSIS

Extend automation in stages

Start with monitoring, diagnosis and operator-reviewed recommendations; expand to supervised control only when data quality and service constraints are demonstrated.

Expected-performance models and digital twins are technical extensions. Keep operator override, equipment interlocks and fallback sequences independent of the optimizer.

Platform layer
LayerFunction
Meter / BMSAcquire timestamped energy and operating states
Data qualityBoundary, completeness and meter version
KPI / diagnosisPUE, cooling efficiency and equipment drill-down
Optimization / M&VReview actions and verify adjusted-baseline results

APPLY TO YOUR SITE

Connect your operating data to an actionable energy strategy.

Discuss the measurement boundary, data quality, operating constraints and verification approach for your facility.

Discuss your project All English cases