CASE73 · Data centers · Cooling-tower temperature reset

Balancing chiller and tower electricity through condenser-water temperature reset

Cooling-tower leaving-water temperature is reviewed as a controllable plant variable. Lower water temperature can reduce chiller lift while increasing tower fan energy.

01 · CASE ANALYSIS

Optimize the combined plant

The source evaluates cooling-tower temperature control as an improvement alternative. A fixed low setpoint is not automatically the lowest-energy choice.

Compare chiller, condenser-water pump and tower fan electricity while maintaining required cooling service.

02 · CASE ANALYSIS

Separate approach and range

Tower approach is leaving-water temperature minus outdoor wet-bulb temperature. Range is entering-water temperature minus leaving-water temperature.

These measurements address different questions: closeness to the wet-bulb condition and the water-side temperature drop. Evaluate them at comparable load, water flow and fan operation.

Tower definitions
MetricDefinition
ApproachLeaving water − outdoor wet-bulb temperature
RangeEntering water − leaving water
Plant electricityChiller + relevant pumps + tower fans

03 · CASE ANALYSIS

Test load- and weather-dependent reset

Develop feasible setpoint bands using equipment limits and measured performance. Trial changes in small steps and monitor chiller stability and tower power.

Climate determines attainable water temperature, but approach, equipment condition and hydraulic distribution also matter.

04 · CASE ANALYSIS

Make the result attributable

Use matched heat load and weather or an adjusted plant baseline. Do not count chiller savings without the tower/pump response.

CASE73 is an alternative and economics review. The source does not report an isolated implemented saving or a universal optimum water temperature.

Reset-test checks
CheckReason
Wet-bulb and loadFair comparison
Fan power and speedTower penalty
Chiller operating limitsFeasible setpoint
Total plant kWhNet saving boundary

APPLY TO YOUR SITE

Connect your operating data to an actionable energy strategy.

Discuss the measurement boundary, data quality, operating constraints and verification approach for your facility.

Discuss your project All English cases