01 · CASE ANALYSIS

PUE starts the investigation

On 16 August 2017 at 13:00, a room/floor PUE of 1.848 exceeded the center average of 1.576. Inspection found cooling units operating fans without active cooling.

The observed gap of 0.272 is not itself a savings claim; it identifies the equipment states that require operational review.

02 · CASE ANALYSIS

Weekly analysis and measurement quality

After June metering/data integration and UPOS construction, weekly Monday–Sunday operating records were analyzed, discussed in task-force meetings and converted into center-specific actions.

Only one center had adequate measurement consistency at the time; several others were still undergoing validation/calibration. Cross-center benchmarking waited for comparable data.

Diagnostic event
TimeRoom/floor PUECenter PUEObserved gap
16 August 2017, 13:001.8481.5760.272

03 · CASE ANALYSIS

Pilot fan replacement and scaling

Two centers piloted EC-fan replacement and reported 63.5% lower fan power from before/after comparison: saving = (Pbefore − Pafter) / Pbefore × 100.

A later expansion estimate covered approximately 400 cooling units, with 55% fan-power reduction, KRW 1.1 billion/year benefit and approximately two-year payback. Individual pilot kW values are not available in the public source.

04 · CASE ANALYSIS

Free cooling and tower-test status

Free-cooling expansion was evaluated at KRW 426 million/year potential, KRW 1.757 billion investment and approximately 4.13-year simple payback.

Cooling-tower seasonal setpoint tests were still in progress at the intermediate-report date. No completed temperature-change or tower-energy result is invented.

Evidence ladder
MeasureReported quantityEvidence status
EC-fan pilot63.5% fan-power reductionTwo-center pilot result
Approximately 400-unit expansion55%; KRW 1.1 billion/year; KRW 2.2 billion investmentEstimated rollout
Free-cooling expansionKRW 426 million/year; 4.13-year paybackInvestment-study potential
Tower seasonal settingsTests in progressNo completed saving quantified

05 · CASE ANALYSIS

Continuous improvement lesson

Move from PUE anomaly to cooling/system diagnosis, equipment cause, small-scale tests, economics and M&V. Balance tower fan electricity against downstream cooling effects.

The broader program also reviewed pumps, chiller/cooling-unit COP, service temperatures and support loads. CASE38 presents a related program overview; its figures should not be added again.

APPLY TO YOUR SITE

Connect your operating data to an actionable energy strategy.

Discuss the measurement boundary, data quality, operating constraints and verification approach for your facility.

Discuss your project All English cases