Setting an 8% utility target and a production-linked monthly M&V baseline
Limited monthly electricity records, low chilled-water ΔT and compressor unloading evidence support a utility optimization target. A monthly factor adjusts expected utility use to production-equipment electricity.
01 · CASE ANALYSIS
Operating challenge
Production-equipment electricity changed relatively little while supporting utility electricity increased. Monthly records were insufficient for precise chiller/pump performance analysis.
Measured chilled-water ΔT was 3.8°C in April, 3.1°C in July and 3.4°C in October against an 8°C design value. Compressor unloading consumed about 11% of compressor electricity. Seasonal utility behavior required a monthly baseline.
02 · CASE ANALYSIS
Target basis and factor model
Cooling performance was estimated at about 0.60–0.64 kWh/RT using prior facility benchmarks, with a reference mean around 0.646. Compressed-air benchmark mean was approximately 0.117. Together with low ΔT and unloading, the report judged approximately 8–10% potential and selected an 8% project target.
For month m, Factor(m) = [baseline total electricity(m) − baseline production electricity(m)] / baseline production electricity(m). Savings(m) = current production electricity(m) × agreed baseline Factor(m) − [current total electricity(m) − current production electricity(m)]. Production electricity is an activity proxy, not a direct production-volume measurement.
| Year | Reported factor |
|---|---|
| 2016 | 2.80 |
| 2017 | 2.62 |
| 2018 | 2.92 |
| Three-year average | 2.78 |
03 · CASE ANALYSIS
Operating improvement scope
Review cooling demand, valves, pumping and chiller balance to address low ΔT. Adjust compressor combinations, loading/unloading and pressure to demand, and align AHU/other-utility operation with production and seasons.
The report cites prior low-ΔT field experience of about 5–10% cooling-system savings, but that is background experience, not a measured result at this copper factory.
04 · CASE ANALYSIS
Baseline agreement and M&V
Agree before implementation whether to use the most recent year’s monthly factors or the three-year monthly means. The source considers recent-year behavior practical, while longer means can moderate individual-year abnormalities.
For precise potential analysis, obtain at least a week of seasonal 5–10-minute chiller/pump power, chilled-/cooling-water temperatures and valve-position records. The 8% remains a target until actual reporting-period data are evaluated against the agreed baseline.
| Item | Value |
|---|---|
| AHUs | 9,920,170 kWh |
| Compressed air | 2,241,097 kWh |
| Chillers | 6,379,070 kWh |
| Other utilities | 13,969,977 kWh |
| Measured chilled-water ΔT | 3.1–3.8°C versus design 8°C |
| Compressor unloading electricity | Approximately 11% |
| Project target | 8%; confirm with agreed monthly-factor M&V |
05 · CASE ANALYSIS
Engineering lesson
A pragmatic proxy baseline can support M&V when detailed data are scarce, but its boundary and assumptions must be agreed. Do not present benchmark-derived targets as measured equipment savings.
APPLY TO YOUR SITE
Connect your operating data to an actionable energy strategy.
Discuss the measurement boundary, data quality, operating constraints and verification approach for your facility.
Discuss your project All English cases